Nature has given man the skill to make changes. But these changes must follow the nature’s own trajectory. Nature will take revenge if we do not follow her natural course
==
BLURB
The true cause of the 2013 disaster was that the High Normal rainfall carried with it boulders, trees and huge amounts of loose earth. The boulders and tree logs blocked the gates of the hydropower projects under construction at Phata-Byung and Singoli-Bhatwari on the Mandakini. The river could not carry these materials downstream as its path had been obstructed. These materials got deposited in the riverbed. The level of the riverbed rose due to this deposition. The rising level of water then scoured and submerged many villages like Chandrapuri lying on the banks of the river
TEXT
It today is the day of Uttarakhand floods that killed many. Anger of the mountains has not subsided two years after the 2013 disaster. Landslides continue to happen regularly and the Char Dham Yatra is reviving but slowly. A reason is that the spree of road-making, hotel construction and hydropower tunneling that were the cause of the disaster continues unabated.
First, let us clear some misconceptions. The rainfall during 16-18 June, 2013 was higher than normal but not uncommon. The Meteorological department says that rainfall in the six affected districts of Uttarakhand between 16 and 18 June was between 59 and 160mm per day. The rainfall at six stations in Kumaon and two stations in Garhwal was more than 173mm per day with the maximum of 237mm recorded at Mukteshwar. Rainfall in the affected area was much less than in other non-affected areas. This clearly establishes that the disaster was not due to “excessive” rainfall though it was certainly higher than normal. The expert panel constituted under orders of the Supreme Court has pointed out that nine districts received heavy rainfall during the same period.
The fact that rainfall was not unusual has also been noted in reports of the Wadia Institute, Disaster Mitigation & Management Centre of the Uttarakhand government and the ministry of water resources. Yet, some “experts” continue to harp on the excessive rain quoting non-existent sources. Indeed, the outburst of the glacial lake at Chorabari Tal upstream of Kedarnath added to the High Normal rainfall. But the lake was relatively small and such outbursts happen regularly in the Himalayas. There was nothing exceptional in this.
A second misconception is that the Tehri Dam arrested the flow from Bhagirathi and Bhilangana rivers and prevented Haridwar from being flooded. It is true that flow at Haridwar would be more had Tehri Dam not been there. However, it is doubtful if any damage would have occurred at Haridwar had this water reached the city. The riverbed is wide here and the increase in water level due to this additional water would be small. The earlier floods of this magnitude did not flood Haridwar. Secondly, most damage would have been inflicted on the illegal structures built on the Ganga plain rather than the city proper. It would perhaps be correct to say that Tehri Reservoir helped prevent damage to these illegal structures but there is no evidence whatsoever that the increase in water level in the absence of Tehri Reservoir would have inflicted any damage to the city of Haridwar.
The true cause of the disaster was that the High Normal rainfall carried with it boulders, trees and huge amounts of loose earth. The boulders and tree logs blocked the gates of the hydropower projects under construction at Phata-Byung and Singoli-Bhatwari on the Mandakini. The river could not carry these materials downstream as its path had been obstructed. These materials got deposited in the riverbed. The level of the riverbed rose due to this deposition. The rising level of water then scoured and submerged many villages like Chandrapuri lying on the banks of the river. It also led to a huge reservoir being created behind the Phata-Byung Barrage. This reservoir flooded the bridge at Sitapur and prevented pilgrims from reaching to the safety of the south bank of the Mandakini.
Geologist KS Valdiya writes that the stones in the area are soft and fractured and even a small blow would lead to their collapse. The National Institute of Disaster Management says that earlier earthquakes had loosened the rocks in the mountains. The Disaster Mitigation & Management Centre, Uttarakhand says that blasting for road construction led to increased landslides. The expert panel constituted under orders of the Supreme Court pointed out that the damage was restricted to the upstream and downstream of the four hydropower projects that obstructed the path of the rivers — Vishnu Prayag and Srinagar on the Alaknanda and Phata-Byung and Singoli-Bhatwari on the Mandakini. This is mainly due to blocking of the path of the river by hydropower barrages. The expert panel also points out that hydropower projects have not been designed properly. The Phata-Byung project, for example, was designed for a maximum flood of 1106 cubic meters per second while the water flow during the disaster was 1597 cubic meters per second.
The road-making and hydropower tunneling activities have contributed to the making of the disaster by use of explosives. Geologists have pointed out that the rocks of these mountains are fractured and soft and have already been loosened by the earthquakes. Indiscriminate use of explosives for cutting the hills for road-making and for boring into the hills for making hydropower tunnels have made things worse. The vibrations from these explosions have loosened the rocks yet more. Huge amounts of explosives used for road- making and hydropower tunneling in the area loosened the mountains and the rocks came tumbling down in the High Normal rainfall.
These road and hydropower projects also contributed to the disaster by dumping vast amounts of muck into the riverbed. The Union environment ministry permits these developers to dump the muck on the river banks and secure it with stone walls so that it does not flow into the river. But corruption in road-making and cost-cutting in hydropower projects leads to these guidelines being rarely followed, with the result that the muck is carried by the river when there are floods. A part of the muck got deposited in the riverbed and raised the level of the river and led to increased flooding. Secondly, this muck-laden water worked as a sandpaper and scoured the banks leading to thousands being rendered homeless.
The expert appraisal committee of the ministry of environment, forests and climate change is responsible for giving ‘environment clearances’ to these projects. The committee is often headed by hydropower proponents who have least knowledge of environment. At least two of the chairmen in the recent period have been retired bureaucrats from the power ministry. As a result, the environmental impacts of the projects are not taken on board and clearances are provided with cosmetic safeguards. The expert appraisal committee has an acclaimed record of not rejecting a hydropower project in the last two decades! There is a need for the government to take a relook at the clearance process so that such manmade disasters are not repeated. Nature has given man the skill to make changes. But these changes must follow the nature’s own trajectory. Nature will take revenge if we do not follow her natural course.
The writer is a former Professor of Economics at IIM Bangalore