MLA-LAD funds unspent in 47 constituencies

Odisha Assembly

By RABINARAYAN JENA, OP

Bhubaneswar: Serious lapses have come to the fore in utilisation of MLA Local Area Development (MLA-LAD) funds in the state, with as many as 47 out of the 147 Assembly constituencies recording zero expenditure during the 2024-25 and 2025-26 financial years.

The MLA-LAD scheme was introduced to support development projects across the constituencies. However, several proposed projects are yet to see the light of day due to delays in approval, non-release of funds and failure to utilise the allocated amounts.

In some cases, projects recommended by MLAs have not received government approval, while in others, legislators have been unable to spend the funds released for development works. Delays in submitting utilisation certificates (UCs) for previously spent amounts have also emerged as a major hurdle, affecting the implementation of development projects.

According to information placed before the Assembly, 47 constituencies have not spent a single rupee under the scheme during the two financial years. Additionally, government grants have not been released to 13 constituencies.

Notably, all seven Assembly constituencies in cyclone-hit Ganjam district have reported zero expenditure, raising concerns over the pace of development in the affected region. The figures were shared by Chief Minister Mohan Charan Majhi in the Assembly in response to a question raised by MLA Ranendra Pratap Swain regarding the utilisation of MLA-LAD funds across the state.

According to the data presented by Chief Minister Mohan Charan Majhi in the Assembly Thursday, seven constituencies recorded zero expenditure under the MLA LAD scheme during the 2024- 25 financial year. These include Deogarh, Paradip in Jagatsinghpur district, Sukinda in Jajpur district, Brajarajnagar and Jharsuguda in Jharsuguda district, Bhawanipatna in Kalahandi district, and Mahakalpada in Kendrapada district.

Similarly, during 2025-26, not a single rupee was spent in seven Assembly constituencies of Ganjam district — Bhanjanagar, Digapahandi, Gopalpur, Hinjili, Polasara, Sanakhemundi and Sorada. The figures further reveal that no projects were approved in 13 Assembly constituencies during 2025-26 financial year. A total of `731.32 crore was allocated for the scheme in that financial year.

While projects worth `577.55 crore were recommended by legislators, proposals amounting to `402.30 crore received government approval. However, only `77.23 crore was actually spent. For financial year 2026-27, the government informed all District Collectors through a letter dated October 7 about utilisation of MLA-LAD funds.

However, the funds are yet to be released. The 13 constituencies where not a single project has received approval are: Digapahandi, Sanakhemundi, Bari, Begunia, Ekamra-Bhubaneswar, Jayadev, Laxmipur, Morada, Nayagada, Bissam Cuttack, Biramitrapur, Bonai and Rourkela.

The overall unspent amount under MLA-LAD scheme across Odisha has exceeded `654.09 crore, highlighting the extent of underutilisation of funds earmarked for constituency-level development. Questions have also been raised over delays in utilising the funds and the failure of officials to submit the required utilisation certificates on time.

Responding to the concerns, the Chief Minister said revised guidelines have prescribed specific timelines for each stage of the scheme to ensure faster implementation. He added that the progress of development works would also be monitored through a dedicated online portal for MLA-LAD funds.

Despite hundreds of crores of rupees being allocated for constituency development, the failure to utilise the funds has triggered political concerns over the efficiency and accountability of both elected representatives and the administrative machinery.